OUR TRACK RECORD

Power

Works performed include:
 

  • 66kv Feeder Cables, Transformers, Conduits and Pits
  • Pad Mount Transformer Installations
  • Service Pillar Installations
  • Stobie Pole Footings
  • Substation Construction inclusive of concrete transformer bunds and Blast Walls
  • Structural Bunker construction and installation of under ground HV Conduits and Class D concrete Pits

Power Project Highlights

SEACLIFF MINI HYDRO | SA WATER

Seacliff Mini Hydro involved the design, construction and commissioning of dual 11kV feeders to the SAPN grid, stobie poles, pad mount transformer, 1 MVA Gilkes Minihydro unit, mechanical pipeworks, earthing, electrical and associated SCADA to enable
1 MVA to generate to the grid. Managed by Nick Valenzisi whilst working for John Holland.

TRACTION POWER SUBSTATION | DPTI

Traction Power Substation Construction for the Seaford Rail Line Electrification
Managed by Nick Valenzisi whilst working for John Holland.

SUNDROP FARMS

Bulk earthworks, structural, mechanical and electrical works for the Port Augusta Sundrop Farms Project. Design and early works managed by Nick Valenzisi whilst working for John Holland.

Water/Waste Water

Team Civil have delivered numerous projects for SA Water and we are their preferred Panel Contractor for Cathodic Protection Installation, with this contract in place since 1993.

Projects undertaken include:
 

  • Mt Gambier Trunk Main Valve Replacements
  • Hackney Road Trunk Water Main Replacement
  • Hackney Road Sewer Modifications and Extensions
  • Darlington Sewer Main Renewal

Water/Waste Water Project Highlights

 

HOPE VALLEY RESERVOIR TO GILBERTON UPGRADE | SA WATER

Replacement of multiple large diameter valves and MSCL piping, inclusive of Cathodic Protection works for the Hope Valley Reservoir to Gilberton Pump Station Trunk Water Main Upgrade.

This project was project managed by Nick Valenzisi whilst working for Fulton Hogan. Team Civil were involved in these works for the Cathodic Protection Installation.

MANNUM TO ADELAIDE PIPELINE
SA WATER

Mannum to Adelaide pipeline DN1500 MSCL pipework investigation upgrades.

DARLINGTON GATEWAY SOUTH PROJECT
SA WATER & DPTI

Sewer and water pipework installation for the Darlington Gateway South Project

Managed by Nick Valenzisi whilst working for Gateway South

Cathodic Protection

Works performed include:

  • SA Water sole sourced Cathodic Protection contractor since 1993 and specialist panel member
    since 2012
  • Kangaroo Island TWM CP upgrade inclusive of Impressed Current System (SA Water)
  • Port Road TWM CP upgrade inclusive of Impressed Current System (SA Water)
  • Morgan to Whyalla CP Upgrade for the Spencer Gulf TWM Crossing inclusive of Impressed Current System (SA Water)
  • Port Lincoln TWM CP upgrade inclusive of Impressed Current System (SA Water)
  • Elizabeth TWM Cathodic Protection upgrade
  • Transformer Rectifier Unit and SCADA works for Kangaroo Island Trunk Water Main
  • Mannum to Adelaide pipeline upgrades
  • Spencer Gulf TWM CP Upgrades
  • Gumeracha CP Upgrade

Cathodic Protection Project Highlights

 

KANGAROO ISLAND TWM | SA WATER

Vertical Drilling of anode beds for an Impressed Current Cathodic Protection System for the Kangaroo Island TWM Cathodic Protection upgrade.

KANGAROO ISLAND TWM | SA WATER

Transformer Rectifier Unit and SCADA works for Kangaroo Island Trunk water Main (TWM) impressed current Cathodic protection system.

OLYMPIC DAM | BHP LEED

Cathodic Protection for the Borefields Pipeline Project, Roxby Downs (BHP)

General Infrastructure

Team Civil Managing Director Nick Valenzisi has worked on a number of DPTI projects prior to the buyout of Team Civil. 

Works completed include:
 

  • Seaford Rail Electrification
  • South Rd Superway Upgrade
  • South Rd Darlington Upgrade
  • Park Tce Metro Rail Grade Separation
  • Team Civil have provided construction consulting and contracting services in Australia to numerous tier-one construction companies, including: John Holland, Fulton Hogan, Lendlease, Lange O’Rourke, LEED Engineering, York Civil, Bardavcol and SEM Group.

General Infrastructure Project Highlights

 

DARLINGTON ROAD UPGRADE | DPTI

Road Lighting, Traffic Signal and Intelligent Transport system (ITS) underground conduits and pits installed on the Darlington road upgrade for the Department of Transport and Infrastructure (DPTI). Managed by Nick Valenzisi whilst working for Gateway South.